Zibo Qixiang Tengda "200,000 tons/year maleic anhydride expansion project" granulation system passed acceptance and put into production and operation

Zibo Qixiang Tengda "200,000 tons/year maleic anhydride expansion project" granulation system passed acceptance and put into production and operation

  • Categories:News
  • Time of issue:2022-04-25

(Summary description)The 200,000 tons / year maleic anhydride project of Zibo Qixiang Tengda Chemical Co. , Ltd. selected the complete set of granulation molding system equipment and the central control DCS control system designed and manufactured by our company, and was officially put into use at the Zibo site on April 18 , 2022 . Production runs and produces qualified maleic anhydride granules.

Zibo Qixiang Tengda "200,000 tons/year maleic anhydride expansion project" granulation system passed acceptance and put into production and operation

(Summary description)The 200,000 tons / year maleic anhydride project of Zibo Qixiang Tengda Chemical Co. , Ltd. selected the complete set of granulation molding system equipment and the central control DCS control system designed and manufactured by our company, and was officially put into use at the Zibo site on April 18 , 2022 . Production runs and produces qualified maleic anhydride granules.

  • Categories:News
  • Time of issue:2022-04-25 09:11
  • Views:
Information

Zibo Qixiang Tengda Chemical Co., Ltd.

" 200,000 tons / year maleic anhydride expansion project" (phase II) granulation system

Has passed the owner's acceptance and put into production operation

 

The 200,000 tons / year maleic anhydride project of Zibo Qixiang Tengda Chemical Co. , Ltd. selected the complete set of granulation molding system equipment and the central control DCS control system designed and manufactured by our company, and was officially put into use at the Zibo site on April 18 , 2022 . Production runs and produces qualified maleic anhydride granules.

This is the second successful cooperation project of our company after providing a complete set of granulation system for the first phase of 150,000 tons / year maleic anhydride plant of Zibo Qixiang Tengda Chemical Co., Ltd. in 2016 .

This project is also one of the one-time successful start-up projects among many major complete engineering projects of our company since 2022 .

Zibo Qixiang Tengda Chemical Co., Ltd. Phase II 200,000 tons / year maleic anhydride project granulation molding system section adopts the maleic anhydride granulation equipment that our company has devoted itself to research and development, design and manufacture for many years (the designed granulation molding capacity is 120,000 tons / year year), the process of this section is equipped with 3 sets (sets) of dry roller press granulators. Our company provides complete sets of process and equipment design, equipment manufacturing, and central control DCS control system design for the granulation system. The process is novel, And the whole production process can realize DCS automatic control, which can realize continuous production and closed operation.

Maleic anhydride granulation equipment installation and use site

Central control DCS control system

Comparison of maleic anhydride raw material and granulated maleic anhydride granules

Keyword:

Scan the QR code to read on your phone

News Center

Contact us

E-mail: sunup@sunup.com.cn

Add: 50 Tiancheng Road, Binjiang Economic Development Zone, Jiangning District, Nanjing

Tel: 86-25-52401353

Tel: 86-13505173158

 

Nanjing Sunup Granulation Equipment Co., Ltd.
Message
Copyright  ©Nanjing Sunup Granulation Equipment Co., Ltd.  All Rights Reserved.        苏ICP备11026504号-1